GI has performed a complete technical and financial supervision of the rehabilitation of tunnel Žutnica.

Road tunnel is in traffic since 1970, and had no drainage system.

Žutnica tunnel has a length of 215 m¹. The existing tunnel lining, which served as the primary tunnel support, hydro insulation has been added and built a new secondary tunnel lining. Concrete used for the secondary tunnel lining was reinforced with plastic bristles. Rehabilitation of the tunnel was built with a completely new drainage system.

INFRASTRUCTURE

Rehabilitation of Žutnica Tunnel

  • SERVICES RENDERED Engineering Supervision
  • PROJECT SIZE 215 m¹
  • PROJECT VALUE 9,1 mil.kn
  • PROJECT PERIOD 2009
  • INVESTOR Croatian roads

     