Construction engineering supervision of the Peljesac Bridge
Investinženjering provides expert construction engineering supervision on the construction of the Peljesac Bridge. Today, the assembly of the lower pre-drilled reinforced-concrete skeleton of the pilot head at the S8 staircase has begun. The preformed slab consists of three reinforced-concrete segments of the bottom of the sheet and the steel side segments. The planar dimension of the S8 headpiece is 23×29 m, while the height varies from 4m to 5m in the center at the pillar position.